A can do a piece of work in 14 days while B can do it in 21 days . they begin together. but 3 days before the completion of the work ,A leaves off .find the total numbers of daysbtaken to complete the work
Answers
- A can do a work in = 14 days .
- B can do it in = 21 days .
- A left before 3 days of the work .
- we have to Find in how many days the work got completed ?
we can solve it by either taking x , or we can save time by solving LCM method . ( Thats my favourite ) .
Lets solve this now ,,,
LCM of 14 and 21 = 42
→ so, Let Total unit of work that would be done is = 42 units .
Now, since A completed it alone in 14 days ,
→ His efficiency of per day work = 42/14 = 3 unit/day .
________________
Now, since B complete it alone in 21 days .
→ His efficiency of per day work = 42/21 = 2 unit/day .
___________________________
Again now, we can solve it by taking let they work together for X days and than A left .
But i dont wanna solve by any Equation ,
so i will Try to solve it without X now ....
______________________
Since it is Given that A left before 3 days of the completion of the work ,
That means we can say that, only B can work for that last three days ... ( Hope You understand what i m saying) .
Now, we know that , B work = 2 unit /day .
→ so, in last 3 days he did = 2×3 = 6 units of work...
___________________
Now, total work is 42 units , and 6 units of work done by B alone in last three days, that means rest work was done by both of them .......
______________________
→ Total unit of work was = 42 units,
→ Done by B in three days = 6 units .
→ Left work to be done = 42 -6 = 36 units ..
[ i Hope its clear now, this was done by both of them now, , ]
__________________
Now ,
→ A and B per day work = 2+3 = 5 units .
_______________________
= (A+B) Together days + B alone 3 days .
_______________