a can do a piece of work in 14 days while B can do it in 21 days they began together and worked at it for 6 days then a fell ill and b
had to complete the remaining work alone in how many days was the work completed
Answers
Answered by
5
After days A did 6/14=3/7 piece of work, and B 6/21=2/7 piece. The remaining work:
1 - 3/7-2/7= 7/7-5/7=2/7 worked B in 21 * 2/7 = 6days.
The work was in 6+6 = 12 days completed.
Answer: 12 days
Note: If A had not been ill, it's the work would be finished by x days:
x/14 + x/21 = 1
3x/42 + 2x/42 = 1
5x = 42
x = 8.4 days
if my answer is helpful for you then please mark as brain liest
1 - 3/7-2/7= 7/7-5/7=2/7 worked B in 21 * 2/7 = 6days.
The work was in 6+6 = 12 days completed.
Answer: 12 days
Note: If A had not been ill, it's the work would be finished by x days:
x/14 + x/21 = 1
3x/42 + 2x/42 = 1
5x = 42
x = 8.4 days
if my answer is helpful for you then please mark as brain liest
sidharthdhire:
am so sorry but you ate wrong
Answered by
5
A can do the piece of work in 14 days. So in one day A completes 1/14 part of work.
Similarly B completes 1/21 part of work.
They worked together for 6 days. So the work completed by them- So now 5/42 part of work is completed by both in one day. In 6 days they would complete
In 6 days both complete 5/7 part of work.
Now the part of work remaining is
As A falls ill at this stage ; B has to work alone. B completes 1/21 part of work. So he can complete the remaining 2/7 part of work in:-
So in all 6+6=12 days were needed to complete the work.
Similarly B completes 1/21 part of work.
They worked together for 6 days. So the work completed by them- So now 5/42 part of work is completed by both in one day. In 6 days they would complete
In 6 days both complete 5/7 part of work.
Now the part of work remaining is
As A falls ill at this stage ; B has to work alone. B completes 1/21 part of work. So he can complete the remaining 2/7 part of work in:-
So in all 6+6=12 days were needed to complete the work.
Similar questions