A can do a piece of work in 15 days and B alone can do it in 10 days. how much time will both take to finished it together?
Answers
Answered by
1
A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. A alone can finish the remaining work in?
For curricular and extra-curricular.
A can do the work in 15 days.
B can do the work in 10 days.
Together they can do the work in = 1/(1/15 + 1/10) = 30/ ( 2 + 3 )= 6 days.
It is not clear whether they are working together or B alone is doing the work.
Assuming that B works alone and leaves after 5 days, 50% of the work would have been completed.
Then for completing the balance work, A will need = 15/100 * 50 = 7.5 days.
If they have worked together and B leaves after 5 days, then 5/6 th of the work would have been over.
Hence, for finishing the balance work, A will take = 15 * 1/6 = 2.5 days.