A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. How much time will A take to complete the remaining work alone?
Answers
Answered by
3
If B works at it for 5 days and leaves then A alone can finish the remaining work in 7.5 days. Then, ½ of the work will be done by A in = = 7.5 days
pls mark my answer as brainliest
Answered by
5
If B works at it for 5 days and leaves then A alone can finish the remaining work in 7.5 days.
A can complete a work in 15 days
So, In 1-day, A can do =
th of work
B alone can do the work in 10 days
So, In 1-day, B can do =
th of work
But, it is given that B works only for 5 days and then leaves A alone
∴ Amount of work done by B in 5 days =
So, The remaining amount of work that A will do alone is = 1 – ½ = ½
Now,
If
th of work is done by A in 1 day
Then, ½ of the work will be done by A in =
= 7.5 days.
If B works at it for 5 days and leaves then A alone can finish the remaining work in 7.5 days.
Then, ½ of the work will be done by A in = = 7.5 days.
Similar questions