Math, asked by aaravaai465, 8 hours ago

A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. How much time will A take to complete the remaining work alone?

Answers

Answered by kislayraj0
3

If B works at it for 5 days and leaves then A alone can finish the remaining work in 7.5 days. Then, ½ of the work will be done by A in = = 7.5 days

pls mark my answer as brainliest

Answered by Blink07
5

If B works at it for 5 days and leaves then A alone can finish the remaining work in 7.5 days.

A can complete a work in 15 days

So, In 1-day, A can do =

 \frac{1}{15}

th of work

B alone can do the work in 10 days

So, In 1-day, B can do =

 \frac{1}{10}

th of work

But, it is given that B works only for 5 days and then leaves A alone

∴ Amount of work done by B in 5 days =

 \frac{5}{10}  =  \frac{1}{2}

So, The remaining amount of work that A will do alone is = 1 – ½ = ½

Now,

If  

 \frac{1}{15}

th of work is done by A in 1 day

Then, ½ of the work will be done by A in = 

 \frac{15}{2}

= 7.5 days.

If B works at it for 5 days and leaves then A alone can finish the remaining work in 7.5 days.

 Then, ½ of the work will be done by A in = = 7.5 days.

Answered by </p><p></p><p>PRKGoes

\huge\sf\blue{Mark \: As \: Brainlist ☆}

Similar questions