a can do a piece of work in 15 days and b can do the same piece of work in 12 days what part of work they can do in 3 days
Answers
Answered by
5
Answer:
9/20
Step-by-step explanation:
a do the work in 1 day =1/15
b do the work in 1 day =1/12
both do the work in 1 day =1/12+1/15=3/20
- in 3day they do = 9/20