Math, asked by my174305, 10 months ago

A can do a piece of work in 15 days and B can do the same work in 20 days. They worked together for 6
days, then B fell ill, so remaining work was completed by A. In how many days, A completed the work?​

Answers

Answered by airmech
6

Answer: 12 DAYS

Step-by-step explanation:

(A + B)'s 1 day's work

=1/15 + 1/10= 1/6

Work done by A and B in 2 days

= 1/6*2= 1/3

Remaining work

= 1− 1/3 = 2/3

NOW 1/15 WORK ID=S DONE BY A IN 1 DAY

Therefore 2/3 work will be done by A in

15* 2/3=10 days

Hence,the total time taken = 10+2= 12 days

HOPE IT HELPS YOU!!!!

Answered by Avuu586
6

Answer:

In one day A can complete 1/25 of the work. And.

In one day B can complete 1/20 of the work.

Together they can complete 1/25+ 1/20 work in one day.

Hence in 5 days they can complete 5/25 + 5/20 work. ie = 9/20 work.

Remaining work is 1–9/20 work= 11/20 work

Hence B can complete the remaining 11/20 work in 11/20 / 1/20=11 days.

Step-by-step explanation:

Similar questions