Math, asked by tejpal5042, 11 months ago

A can do a piece of work in 15 days and b in 10 days.They work together but a leaves after sometime and b finished the work in 5 days. After how many dates a left the job

Answers

Answered by wwwsatyawansan
0

Answer: A will left the job after 2 days

Similar questions