A can do a piece of work in 15 days and B in 20 days . With the help of C, the work gets finished in 5 days.Hoe long will C take to finish the work alone
Answers
Answered by
4
Answer:
12 days
Step-by-step explanation:
(i)
Given that A can do a piece of work in 15 days.
Amount of work done by A in 1-day = (1/15).
(ii)
Given that B can do a piece of work in 20 days.
Amount of work done by B in 1 -day = (1/20).
(iii)
Work done by (A + B) in 1-day = (1/15) + (1/20)
= 7/60
Now,
Given that With the help of C, the work gets finished in 5 days.
Work done by (A + B + C) in 1-day = (1/5). -------- (iv)
Substitute (iii) in (iv), we get
⇒ 7/60 + C = 1/5
⇒ C = (1/5) - (7/60)
⇒ C = 5/60
⇒ C = 1/12.
Therefore, C will finish the work alone in 12 days.
Hope it helps!