Math, asked by shridharpanda36, 1 month ago

A can do a piece of work in 15 days. B is 50 % more efficient than A . B can finish it in how many days? ???


pls guys hurry up
correct answer will be marked as brainliest. ​

Answers

Answered by jaikishorverma8
1

Answer:

Because efficiency and time taken is inversely proportional to each other. Hence 15 days is 50% more than the time taken by B. B = 15*(100/150) = 10days.

Answered by Anonymous
1

Please find the attached photographs for your answer