A can do a piece of work in 16 days and B can finish it in 20 days. They work together for 4 days and then A leaves. In how many days will B finish the remaining work ?
Answers
Answered by
9
SOLUTION-
Time taken by A to finish the work = 16 days
⟹ Work done by A in one day =
Time taken by B to finish the work = 20 days
⟹Work done by B in one day =
Work done by ( A + B ) in one day
★ Work done by ( A + B ) in four day
Remaining work =
Now , 1/20 of work is done by B in 1 day.
★ the complete work is done by B in 1 ÷ days
★ of work will be done by B in days = 11 days
Hence , B will finish the remaining work in 11 days.
Answered by
2
Answer:
B will finish the remaining work in 11 days
Similar questions