Math, asked by BePro, 8 months ago

A can do a piece of work in 16 days and B can finish it in 20 days. They work together for 4 days and then A leaves. In how many days will B finish the remaining work ?

Answers

Answered by Anonymous
9

SOLUTION-

Time taken by A to finish the work = 16 days

Work done by A in one day =  \dfrac{1}{16}

Time taken by B to finish the work = 20 days

Work done by B in one day =  \dfrac{1}{20}

Work done by ( A + B ) in one day

⟹( \dfrac{1}{16}  +  \dfrac{1}{20})

⟹\dfrac{9}{80}

★ Work done by ( A + B ) in four day

⟹ \dfrac{9}{80}  \times 4 =  \dfrac{9}{20}

Remaining work = (1 -  \dfrac{9}{20} ) =  \dfrac{11}{20}

Now , 1/20 of work is done by B in 1 day.

★ the complete work is done by B in 1 ÷  \dfrac{1}{20} days

 \dfrac{11}{20} of work will be done by B in (20 \times  \dfrac{11}{20} ) days = 11 days

Hence , B will finish the remaining work in 11 days.

Answered by QueenSaanvi
2

Answer:

B will finish the remaining work in 11 days

Similar questions