Math, asked by niranjanbaskey1528, 1 year ago

A can do a piece of work in 16 days, B can do in 32 days and C can do in 48 days. After starting together, B left the work 6 days before the end of work and C left 8 days before finishing the work.​

Answers

Answered by Anonymous
3

Answer:

hope it will helps u...

Let the work be completed in= N- days.

Let the work be completed in= N- days.A- works for complete period.

Let the work be completed in= N- days.A- works for complete period.B- works for 8- days

Let the work be completed in= N- days.A- works for complete period.B- works for 8- daysC- works for (N-8) - days.

Let the work be completed in= N- days.A- works for complete period.B- works for 8- daysC- works for (N-8) - days.So N/16 + 8/32+ (N-8)/48= 1

Let the work be completed in= N- days.A- works for complete period.B- works for 8- daysC- works for (N-8) - days.So N/16 + 8/32+ (N-8)/48= 1=6N+ 24+ 2(N-8)= 96

Let the work be completed in= N- days.A- works for complete period.B- works for 8- daysC- works for (N-8) - days.So N/16 + 8/32+ (N-8)/48= 1=6N+ 24+ 2(N-8)= 96= 8N= 96–24+16= 88

Let the work be completed in= N- days.A- works for complete period.B- works for 8- daysC- works for (N-8) - days.So N/16 + 8/32+ (N-8)/48= 1=6N+ 24+ 2(N-8)= 96= 8N= 96–24+16= 88So N= 88/8

Let the work be completed in= N- days.A- works for complete period.B- works for 8- daysC- works for (N-8) - days.So N/16 + 8/32+ (N-8)/48= 1=6N+ 24+ 2(N-8)= 96= 8N= 96–24+16= 88So N= 88/8= 11-days.

Therefore work will be completed in = 11- days.

mark me as a brainlist...