A can do a piece of work in 16 days ,B can do it 12 days .With the help of C they can finish it in 4 days .Then c alone can do it in how many days?
Answers
Answered by
34
Answer :-
C alone can do the same work in 9.6 days.
Solution :-
A can do a piece of work in 16 days
So A's one day work = 1/16
B can do the same work in 12 days
So B's one day work = 1/12
A, B, C can do the same work in 4 days
(A, B , C)'s one day work = 1/4
We know that
C's one day work = (A, B, C)'s one day work - A's one day work - B's one day work
= 1/4 - 1/16 - 1/12
= (12 - 3 - 4)/48
= (12 - 7)/48
= 5/48
C's one day work = 5/48
So C alone can do the same work in 48/5 days i.e 9.6 days.