a can do a piece of work in 18 days B is 20% more efficient than a the number of days B takes to complete the same piece of work is
Answers
Answered by
7
answer is 15 days for B
Attachments:
srikarphani:
hi
Answered by
7
B takes 15 days to complete the same piece of work.
Step-by-step explanation:
Since we have given that
Time taken by A to do a piece of work = 18 days
Ratio of efficiency of B to A is given by
120 : 100
= 6 : 5
(As B is 20% more efficient than A)
Number of days for B would be
Hence, B takes 15 days to complete the same piece of work.