A can do a piece of work in 20 days and B can do the same piece of work in 25 days. They work together for 10 days and then A leaves the work. In how mgny days will A finish the remaining work ?
Answers
Answered by
1
Answer:
12 days i suppose
Explanation:
if right please mark as brainlist