A can do a piece of work in 20 days and B in 24 days. If A, B and C together can complete it in 6 days, in what time would C alone do it?
Answers
Answered by
0
Step-by-step explanation:
C's efficiency = 12−3−4=5
C will complete total work
=605=12 days