A can do a piece of work in 20 days and B in 25 days. How long

will they take together to finish it​

Answers

Answered by spremjitsinghmartins
0

Answer:

a=20

b=25

ain 1 day =1/20

b in 1 day= 1/25

they together= 1/20+1/25

=9/100 theres it

Attachments:
Answered by rishabh994
0

Answer:

Work done by A = 20 days

Work done by A in 1 day = 1/20

Similarly, Work done by B in 1 day = 1/25

Now, they will work together in 1 day =

Work done by A in 1 day + work done by B in 1 day

 →\frac{1}{20}  +  \frac{1}{25}

 →\frac{25 + 20}{500}  =  \frac{45}{500}

 → \frac{9}{100}

Now, No. of days taken by A and B to complete the work together is 100/9 days = 11.11 days

Hope you find it helpful.