Math, asked by AakashSky7986, 1 year ago

A can do a piece of work in 20 days and b in 25 days. They work together for 5 days then b goes away. In how many days will a complete the ramaining work

Answers

Answered by MsPRENCY
6

\bf {\huge {\underline {\boxed {\sf\purple {Answer:\: {13}\dfrac {3}{5}\: days  }}}}}

\textbf {\underline{\underline{Step-By-Step\:Explanation:-}}}

\textbf{\pink {\underline{Given:}}}

  • A can do a piece of work in 20 days
  • B can do in 25 days
  • They both worked together for 5 days
  • Then, B goes away.

\textbf {\underline {\underline {To\:Find:}}}

  • A can finish the work in how many of days

\huge\underline\green {\tt Solution:}

Let work done be ' w '

Now,

Work done by A in 20 days

= \dfrac{w}{20} ------ ( of 1 day )

Work done by B in 25 days

= \dfrac {w}{25} ----- ( of 1 day )

When they worked together,

 =  \frac{5w}{20}  +  \frac{5w}{25}

= \cancel{\dfrac{5}{20}} + \cancel{\dfrac {5}{25}}

 =  \frac{w}{4}  +  \frac{w}{5}

 =  \frac{9w}{20}

Now,

After B left the work,

 = w -  \frac{9w}{20}

 = > \frac{20w - 9w}{20}  = \:  \frac{11w}{20}

•°• \dfrac{11w}{20} is to be done by B. Therefore,

 =  \frac{11w}{20}  \times  \frac{25}{w}  \\  \\   = \frac{55}{4} \\  \\  = 13 \times \frac{3}{5}   \\  \\

= 13. 75 days

Answer : A will take {13}\dfrac {3}{5} days.

Answered by sanvi7031
6

Answer:

  • A will complete his work in 11 days.

Step-by-step explanation:

Work done by A in one day

 =  \frac{1}{20}

Work done by B in one day

 =  \frac{1}{25}

Work done by A and B in one day

 =  \frac{1}{20}  +  \frac{1}{25}  \\  =  \frac{9}{100}

Work done by A and B five days

 = 5 \times  \frac{9}{100}  =  \frac{9}{20}

Remaining work

 = 1 -  \frac{9}{20}  =  \frac{11}{20}

 \frac{1}{20}  \: work \: is \: done \: by \: a \: in \: one \: day. \\  \frac{11}{20 } \:  \: work \: is \: done \: by \: a \: in \: one \: day \:

 =  \frac{11}{20}  \times  \frac{20}{1}  \\  = 11days

Similar questions