Math, asked by vignesh987, 3 months ago

a can do a piece of work in 20 days .b can do it in 25days.both of them finished and earned 3600.then a share is​

Attachments:

Answers

Answered by mailtobidita
0

Answer:

A's 1 day's work =

25

1

Similarly, B's 1 day's work =

20

1

A's and B's together 1 day's work

25

1

+

20

1

=

100

4

+

100

5

=

100

4+5

=

100

9

Their 5 day's work together = 5 x 1 day's work

1−

100

45

=

100

100

100

45

=

100

100−45

=

100

55

Now, this remaining work is done by B.

Let B takes x days to complete it.

20

1

×x=

100

55

⇒x=

100

55

×20

⇒x=

5

55

⇒x=11

Hence, B will finish the remaining work in 11 days.