Math, asked by js29091971, 9 months ago

A can do a piece of work in 20 days,B in 30 days and C in 40 days . They start working together. A works for 2 days and leaves and B works for 4 days and leaves.How long does the work last​

Answers

Answered by SwarnaKumar
2

Answer:

28

Step-by-step explanation:

A efficiency 6

B efficiency 4

C efficiency 3

Total work 120

A+B+C=2 DAYS

B+C=4 DAYS

C=22 DAYS

TT=28...

  • Detailed explanation is given in photo
Attachments:
Answered by devindersaroha43
39

Answer:

Step-by-step explanation:

A does (1/20)th of the work in 1 day.

B does (1/30)th of the work in 1 day.

C does (1/40)th of the work in 1 day.

In the first 4 days, A, B and C did 4[(1/20)+(1/30)+(1/40)] =4{6+4+3]/120 = 13/30th of the work.

In the next 2 days, B and C did 2[(1/30)+(1/40)] = 2*7/120 or 7/60th of the work.

So in the first 6 days the work done was (13/30)+(7/60) = (26+7)/60 = 33/60 or 11/20th of the whole. What remained to be don after the first 6 days was (9/20)th of the whole.

The remaining (9/20)the was done by C alone in (9/20)*(40/1) = 18 days.

Thus the whole work is done in 24 days from the start. Answer.

Similar questions