Math, asked by himanshuharideo, 10 months ago

A can do a piece of work in 20 days which B alone can do in 12 days.B worked at it for 9 days. A can finish the remaining work in.​

Answers

Answered by dibyabapuni128
0

Answer:

5days

Step-by-step explanation:

In 9 days B already done 75% of total work.

Remaining 25% work done by A= 0.25×20

=5