A’ can do a piece of work in 20 days which ‘B’ alone can do in 12 days. ‘B’ worked at it for 9
days then ‘A’ can finish the remaining work in :
Answers
Answered by
7
In 1 day A can do 1/20 part of the work
In 1 day B can do 1/12 part of the work
By working for 9 days B can do
A can do it in 1/4 / 1/20 days
A can do it in 5 days
In 1 day B can do 1/12 part of the work
By working for 9 days B can do
A can do it in 1/4 / 1/20 days
A can do it in 5 days