A can do a piece of work in 20 days while B can do it in 15 days. With the help of C, they finish the work in 5 days. In what time would C alone do it?
Answers
Answered by
3
- A can do a piece of work in 20 days
- B can do it in 15 days
- with help of C they did the work in 5 days
- Find the time required by C for doing the work alone
- A 20 days
- B 15 days
- A + B + C = 5 days
C takes 12 days to complete the work alone.