A can do a piece of work in 20days while B can do it in 15days. With the help of C, they finish the work in 5days. In what time would C alone do it
Answers
Answered by
3
Answer:
ans : 12 days
Step-by-step explanation:
Work by A- 1/20
work by B- 1/15
Total work done by all - 1/5
work by C - 1/c
now add all = 1/20 + 1/15 + 1/c = 1/5
lcm is 60 .
4+3-. 12/60 = - 1/c
7-12/60 = -1/c
-5/60= -1/c
minus minus cancel.
cross multiplication
5c = 60
c= 60/5
c= 12
therefore the time taken by c alone to do a piece of work is 12 days.
pls mark the brainliest answer .and follow me
HOPE IT HELPS YOU
Answered by
0
Step-by-step explanation:
AnswEr:
A & B can do work in 12 Days.
B & C can do work in 15 Days.
C & A can do work in 20 Days.
Now,
• A & B can do work in 1 day =
-------Eq(1)
• B & C can do work in 1 day =
-------Eq(2)
• C & A can do work in 1 day =
-------Eq(3)
From Equations (1) & (2)
-------Eq(4)
Similar questions