A can do a
piece of work in 21 days. B as 75%
more efficient than A. Find the number of days B will
take to do the same work.
Answers
Answered by
0
Answer:
28 days
Step-by-step explanation:
21 = 75% of days of B
LET DAYS OF B BE k
therefore,it takes 28 days for B eorker