A can do a piece of work in 24 days. If b is 60% more efficient than A , how many days B takes to complete the same work?
Answers
Answer:
B will take 15 days to complete the same work.
Step-by-step explanation:
A takes 24 days to complete the work.
B is 60% more efficient than A
Remember:
If a worker is more efficient, he will take less time to complete the same work.
If a worker is more inefficient, he will take more time to complete the same work.
Now, if
B is 60% more efficient than A
=> A is 60% more inefficient than B for the same work
=> A will take 60% more time than B for the same work
Given that
A takes 24 days to complete the work
Let the number of days taken by B = x
=> 24 = 60% more than x
=> 24 = (60% of x) + x
=> 24 = 0.6*x + x
=> 24 = 1.6*x
=> x = (24/1.6)
=> x = 15
B will take 15 days to complete the same work
Alternate Method
A can do the work in 24 days
=> A does (1/24) work in 1 day
If B is 60% more efficient, B can do 60% more work than A in the same time
=> B does [(1/24) + (60% of 1/24)] of the work in 1 day
=> B does {1/24 + 0.6/24] of the work in 1 day
=> B does (1.6/24) of the work in 1 day
=> B takes (24/1.6) days to complete the work
=> B takes 15 days to complete the work
Remember: If a man does (1/n) of the work in 1 days, he will take n days to complete the work.
Question
A can do a piece of work in 24 days. B is 60% more efficient than A. The number of days B take to do the same piece of work is
Answer:
Solution
Let the work done by A be x so,
x = 24 days
As per the question , 60% of x = b
= B's work
Now
If x = 24 days then,
Therefore, B can do the work in 14.4 days (or) 15days.