A can do a piece of work in 24 days.if b is 60% more efficient than A, then the number of days required by B to do the twice as large as the earlier work
Answers
Answered by
2
Answer:
30
Step-by-step explanation:
The total work is 120....
And double the work then it is 240
And divided by b's efficiency.. 8...then you will get ans 30
Attachments:
Answered by
1
The number of days required by B to do the twice as large as the earlier work = 30 days
Step-by-step explanation:
Let efficiency of A = 100
Efficiency of B = 160
Ratio of efficiencies of A & B is = 100 : 160 = 5 : 8
No. of days required to finish the work by A & B are in the ratio = 8 : 5
Since no. of days required by A to complete the work = 24 days
So number of days required to complete the work by B = × 5 = 15 days
If the work is doubled then the number of days required to complete the work by B = 15 × 2 = 30 days.
Similar questions