A can do a piece of work in 24 days. If B is 60% more
efficient than A, then the number of days required by
B to do the twice as large as the earlier work is [1]
(a) 24 (b) 36
(c) 15 (d) 30
can any one of u explain it properly ?
Answers
Answered by
2
Answer:
Step-by-step explanation: Given that A can do a piece of work in 24 days and B is 60% more efficient than A.
So, the number of days required by B to complete the same work = 24/1.6 = 15
So, to complete the twice the work, required days = 2 x 15 = 30
Hence, option (d) is correct.
Similar questions