Math, asked by harish2504, 10 months ago

A can do a piece of work in 24 days. if B is 60% more efficient than A, then B can complete the work in? ​

Answers

Answered by AntareepDey
17

Ans.) B completed the work in 15 days.

Hey mate! Hope this helps!! Please mark as Brainliest!!!

Attachments:
Answered by erinna
38

B can complete the work in 15 days.

Step-by-step explanation:

It is given that A can do a piece of work in 24 days.

One day work of A = \frac{1}{24}

B is 60% more efficient than A.

One day work of B = \frac{1}{24}+\frac{60}{100}\times \frac{1}{24}

One day work of B = \frac{1}{24}+\frac{1}{40}

One day work of B = \frac{5+3}{120}

One day work of B = \frac{8}{120}

One day work of B = \frac{1}{15}            .... (1)

Let B can complete the work in t days.

One day work of B = \frac{1}{t}              .... (2)

From (1) and (2) we get

\frac{1}{t}=\frac{1}{15}

t=15

Therefore, B can complete the work in 15 days.

#Learn more

A can do a piece of work in 24 days. If b is 60% more efficient than A , how many days B takes to complete the same work?

https://brainly.in/question/14195344

Similar questions