A can do a piece of work in 25 days and
B can do the same work in 30 days. They work
together for 5 days and then A leaves. B will
finish the remaining work in?
Answers
Answered by
0
a can do a work in 25 days and b can do it in 30 days
nandu4:
and so it will be 20 days
Answered by
3
A can do a piece of work in 1/25 days .
B can do a piece of work in 1/30 days.
They together work in 1/25 + 1/30 days
25/30 = 30 + 25 / 750 = 55/750th work in the day.
In 5 days A & B together complete 5 × 55/750
= 275/750 = 11/30 of the work.
So, the work left is 1 - 11/30 = 30 - 11 / 30 = 19/30.
i hope it will help u ❤️