Math, asked by pragyarai1801, 8 months ago

A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A leaves. In how many days will B finish the remaining work? ​

Answers

Answered by Anonymous
30

Answer:

11 days

Step-by-step explanation:

A can do a piece of work in 25 days

Work done by A in one day = 1 / 25

B can finish it in 20 days

Work done by B in one day = 1 / 20

A and B started working together

Work done by A and B in one day = 1 / 25 + 1 / 20 = ( 4 + 5 ) / 100 = 9 / 100

A and B work together for 5 days

Work done by A and B in 5 days = 5 × ( 9 / 100 )  = 9 / 20

A leaves after 5 days. So Remaining work is to be done by B

Remaining work done by B = 1 - 9 / 20 = ( 20 - 9 ) / 20 = 11 / 20

11 / 20 work done by B in = ( 11 / 20 ) × 20 = 11

Hence B will finish the remaining work in 11 days.

Answered by Anonymous
26

Given :

  • Number of days A work = 25 days
  • Number of days B work = 20 days
  • Number of days A & B both work =5days

To Find :

  • Number of days B will finish the remaining work

Solution :

▪️Work done by A in 1 day = 1/25

▪️Same Work done by B in 1 day = 1/20

Then,

Total work done by A & B in one day =1/25+1/20

= 45/500

= 9/100

When A & B together work for 5 days, work done will be;

Total work done by A & B in 5 days =5×9/100

= 9/20

Now,

After 5 days when, A leaves the remaining work done by B will be;

Remaining work done by B = 1 - 9/20

= 11 /20

Hence, number of days remaining work done by B = 11×20/20 = 11 days

Therefore, B will finish the remaing work in 11 days.

Similar questions