A can do a piece of work in 25 days and b in 20 days. with the help of c they finish the work in 8 days. how long will it take c alone to finish the work
Answers
Answered by
4
Answer:
200/7=28 4/7
Step-by-step explanation:
Given,
A can do a piece of work in 25 days
A=1/25
b in 20 days.
B=1/20 days
with the help of c they finish the work in 8 days.
A+B+C=1/8 days -----(1)
how long will it take c alone to finish the work
C=1/8-A-B from Eq(1)
C=1/8-1/25-1/20
C=7/200