A can do a piece of work in 25 days which B alone can finish in 20 days. Both together work for 5 days and then A leaves off. How many days will B take to finish
the remaining work?
Answers
Answered by
21
Work done by A in 1 day =
Work done by B in 1 day =
- =>
Both worked for 5 days together =
- => 9 × 5 = 45
Remaining work is done by B
- =>
- Now let B take x days to complete the work.
=>
:. B took 11 days to complete the work alone.
Similar questions