Math, asked by bhavnishsehrawat1, 16 days ago

A can do a piece of work in 25 days which B alone can finish in 20 days. Both together work for 5 days and then A leaves off. How many days will B take to finish
the remaining work?

Answers

Answered by MikeCrystal
21

\huge\mathbb\colorbox{black}{\color{red}{Question}}

  • \sf\red{How \: many \: days \: will \: B \:  take \: to \: finish}
  • \sf\red{the \: remaining \: work?}

\huge\mathbb\colorbox{black}{\color{red}{Answer:-}}

  • \sf\red{11 \: days}

\small\mathbb\colorbox{black}{\color{orange}{Solution \: For \: The \: Correct \: Answer-}}

Work done by A in 1 day =

 \frac{1}{25}

Work done by B in 1 day =

 \frac{1}{20}

  • =>
  •  \frac{1}{25} +  \frac{1}{20}  \\  \\  =  >  \frac{5}{100}  +  \frac{4}{100}  \\  \\  =  >  \frac{5  +  4}{100}  =  \frac{9}{100}

Both worked for 5 days together =

  • \small\bold\orange{5×1 \: day \: work=5}

  • => 9 × 5 = 45

Remaining work is done by B

  • =>
  •  1 -  \frac{45}{100}  \\  \\  =  >  \frac{100}{100} -  \frac{45}{100}  \\  \\  =  >  \frac{100 -4 5}{100}  \\  \\  =  >  \frac{55}{100}
  • Now let B take x days to complete the work.

=>

 \frac{1}{20} \times x =  \frac{55}{100} \\  \\  =  > x =  \frac{55 \times 20}{100}  \\  \\  =  > x =  \frac{1100}{100}  =  > x = 11

:. B took 11 days to complete the work alone.

Similar questions