A can do a piece of work in 3 days.B can do a piece of work in 6days how long would it take to complete the work if a and b did it together

Answers

Answered by shampasaha5970
1

Step-by-step explanation:

A can do a price of work in 3 days

A can do ⅓ price of work in 1 day

B can do a price of work in 6 days

B can do a 1/6 price of work in 1 day

if A and B did it together,

it would took ⅓+1/6

or, 2/6

or, 1/3

= 3days

it would take 3 days long to complete the work if A and B did it together