A can do a piece of work in 30 days and B can do it in 20 days. They work . together for 4 days and then B leaves the job. In how many days, will A finish the remaining work?
Answers
Answered by
2
Step-by-step explanation:
hope it helps you
mark as Brainliest
Answered by
4
Given:—
- A can do a piece of work in 30 days and B can do it in 20 days. They work together for 4 days and then B leaves the job.
To Find:—
- They work together for 4 days and then B leaves the job. ?
Solution:—
→ LCM of 30 and 20 = 60 units = Let total work .
So,
→ Efficiency of A = Total work / Time taken = 60/30 = 2 units / day .
and,
→ Efficiency of B = Total work / Time taken = 60/20 = 3 units / day .
then,
→ Work done by (A + B) in one day
- = (2 + 3)
- = 5 units
so,
→ Work done by (A + B) in first 4 days
- = 5×4
- = 20 units
Now,
→ Work left to be done = 60 - 20
= 40 units
since B left, only A has to complete left work .
therefore,
→ Time taken by A to complete the remaining work = Lefy work / Efficiency of A = 40/2 = 20 days (Ans.)
Hence,
A will finish the remaining work in 20 days .
Similar questions