Math, asked by 10311377, 18 days ago

A can do a piece of work in 30 days and B can do it in 20 days. They work . together for 4 days and then B leaves the job. In how many days, will A finish the remaining work?​

Answers

Answered by eeepathshala
2

Step-by-step explanation:

 \because \: time \: taken \: to \: finish \: the \: work \: by \:  \:  \: a =  \: 30 \: days \\  \therefore \: a  \:  \: s\: 1  \: day \: work =  \frac{1}{30} part \\  \because \: time \: taken \: to \: finish \: the \: work \: by \:  \:  \: b =  \: 20 \: days \\  \therefore \: b  \:  \: s\: 1  \: day \: work =  \frac{1}{20} part \\(a + b) \:  \: s \: 1 \: day \: work =  \frac{1}{30}  +  \frac{1}{20} part \\  =  \frac{2 + 3}{60}  =  \frac{5}{60}  =  \frac{1}{12} \:  part \\ so \: (a + b) \:  \: s \: 4 \: days \: work =  \frac{1}{12}  \times 4 =  \frac{1}{3} \:  part \\ remaining \: work = 1 -  \frac{1}{3}  =  \frac{3 - 1}{3}  =  \frac{2}{3}  \: part \\ so \: time \: taken \: to \: finish \: the \: remaining \: work \: by \: a =  \frac{ \frac{2}{3} }{ \frac{1}{30} }  \\  =  \frac{2}{3}  \times  \frac{30}{1}  = 2 \times 10 = 20 \: days

hope it helps you

mark as Brainliest

Answered by Vikramjeeth
4

Given:

  • A can do a piece of work in 30 days and B can do it in 20 days. They work together for 4 days and then B leaves the job.

To Find:

  • They work together for 4 days and then B leaves the job. ?

Solution:

→ LCM of 30 and 20 = 60 units = Let total work .

So,

→ Efficiency of A = Total work / Time taken = 60/30 = 2 units / day .

and,

→ Efficiency of B = Total work / Time taken = 60/20 = 3 units / day .

then,

→ Work done by (A + B) in one day

  • = (2 + 3)
  • = 5 units

so,

→ Work done by (A + B) in first 4 days

  • = 5×4
  • = 20 units

Now,

→ Work left to be done = 60 - 20

= 40 units

since B left, only A has to complete left work .

therefore,

→ Time taken by A to complete the remaining work = Lefy work / Efficiency of A = 40/2 = 20 days (Ans.)

Hence,

A will finish the remaining work in 20 days .

Similar questions