A can do a piece of work in 30 days, B can do it in 15 days and C can do it in 10
days. If in every second day B and in every third day C help A in doing the work,
how many days will be required to complete the whole work?
Answers
Answered by
0
Answer:
8.67 days
Step-by-step explanation: