A can do a piece of work in 30 days. He works for 15 days and then B alone finishes the remaining work in 40 days.The two together can finish the work in

a. 240/11 days b. 250/11 days
c. 303/11 days d. 320/11 days ​

Answers

Answered by Queen123733733
1

Answer:

in one day, work done by A is =1/30

In one day, work done by B is=1/40

Total work done in one day when A and B works together is =1/30+1/40=7/120

The work will be completed in =120/7 days =17.31 days

Therefore the work will be completed in 17 days +some hours

hope it helps you dear regards (Anshika) Queen123733733