A can do a piece of work in 39 days and B is 30% more efficient than A. In how
many days can B finish it?
Answers
Answered by
0
Number of days A need = 39 days
Number of days B need
= 30% of 39 + 39
= 130 % of 39
= 130/100 × 39
= 50.7
≈ 51 days
Similar questions