A can do a piece of work in 4 days and b can do the same work in 5 days. Find, how much work can be done by them after working together in(1)one day(2)2 days)
Answers
Answered by
5
1/4+1/5=5+4/20=9/20 work done in one day.in 2days=2×9/20=9/10