A can do a piece of work in 4 days and B in 5 days. How long will they take to do the same
work, when working together?
2/25
Answers
Answered by
1
Explanation:
A can do a piece of work in 4 days and B in 5 days. How long will they take to do the same
work, when working together?
2/25
Answered by
1
Explanation:
A completes the work in 4 days
then
A can complete 1 / 4 th of the work in a day
Similarly
B can complete 1 / 5 th of the work
Then A and B can complete (1/4 +1/5 = 9 / 20 th of the work in a day )
both can complete the work in 20/9 days