A can do a piece of work in 4 days B can do it in 5 days and c can do it in 10days. then a b c together can do the work in how many days​

Attachments:

Answers

Answered by Anonymous
8

Work done by A in 1 day = 1/4

Work done by B in 1 day = 1/5

Work done by C in 1 day = 1/10

Work done by ( A+B+C ) i.e., by all of them together in 1 day = ( 1/4 + 1/5 + 1/10 ) = 11/20

Therefore ( A+B+C ) can finish the work in 20/11 days = 1 whole 9/11 days.

Hope this helps you friend......

Be brainly ☺️☺️☺️


sivaprasath: 20/11 days = 1 whole 9/ 20 days (or) 1 whole 9/11 days ??
Anonymous: oops sorry my mistake
mailtosweetammu: Tq ....
mailtosweetammu: I have posted one image also. can u plz solve those problems ??
Anonymous: um I already answered...sorry