A can do a piece of work in 4 hours. a and c together can do it in just 2 hours, while b and c together need 3 hours to finish the same work. b alone can complete the work in --- hours
Answers
Answered by
0
Answer:12 hours
Step-by-step explanation:
Work done by A: 1/4 per hr
Work done by A+C: 1/2 per hr
Work done by B+C: 1/3 per hr
WD by C=WD(A+C)-WD(A)=1/2- 1/4=1/4
WD by B=WD(B+C)-WD(C)=1/3- 1/4=1/12
Hence, Work done by B=12 hrs