A can do a piece of work in 40 days and B in 45 days. They work together for 10 days and then B goes away. In how many days will A finish the remaining work?
Answers
Answered by
3
Please see the attachment
A = 40(9)
B = 45(8)
Total work days = 360
Days worked = 170
Remaining = 360-170/ 9 = 21 1/9
A = 40(9)
B = 45(8)
Total work days = 360
Days worked = 170
Remaining = 360-170/ 9 = 21 1/9
SuyashKumar1:
Your answer is wrong
Answered by
5
21, 1/9 days will be the answer