A can do a piece of work in 40 days. He worked at it
for 5 days, then B finished it in 21 days. The number
of days that A and B take together to finish the work
ane
(A) 15 days
(B) 14 days
(C) 13 days
(D) 10 days​

Answers

Answered by suvratraj79922
1

Answer:

A can do a piece of work in 40 days

Work of A in 1 day=1/40

Work of A in 5 days=5/40=1/8

1/8th part of work is done by A

Remaining work=(1−

8

1

)=

8

7

7/8th part is done by B in 21 days

Total work will be done by B in =

8

7

21

=

7

21

×8=24days

Work done by B in one day=1/24

Work done by A and B together in one day will be(

40

1

+

24

1

)

(

120

3+5

)=

120

8

=

15

1

A and B will take 15 days to complete the work together.