Math, asked by safikei811, 3 months ago

A can do a piece of work in 45 days.He works for 30 days and leaves.If B completes the remaining work in 5 days then in how many days can B alone complete the entire work.

Answers

Answered by IIJustAWeebII
2

Answer:

 \pink{ \boxed{ \large{15 \: days}}}

Step-by-step explanation:

 \red{ \mathfrak{ \large{Given}}}

  • A can do a piece of work in 45 days.
  • He works for 30 days and leaves.
  • B completes the remaining work in 5 days.

 \mathfrak{ \underline{ \underline{ \large{To \: find}}}}

  • The days B can alone do

 \pink{ \mathfrak{ \underbrace{Solution}}}

As, A can do 1(whole) work in 45 days,

Then,

A's 1 day work is 1/45

A's 30 day work is 30/45 = 2/3

Rest of work is (1-2/3) = 1/3

According to the question,

B does 1/3 work in 5 days.

Then,

B does 1 (whole) work in

 =  \frac{ 5 }{ \frac{1}{3} }  \\ =  5 \times 3 \\  = 15

Hence, B does alone can complete the work in 15 days.

❣Hope this helps you✌

Similar questions