Math, asked by juhu11, 1 year ago

a can do a piece of work in 50 days and b can do a work in 100 days.
in how many days both work together

Answers

Answered by 05102005rajat78
1
A =50 days
B=100 days
If both work together then:-
 \\ \frac{1}{days }    =  \frac{1}{50}  +  \frac{1}{100 }  \\  \frac{1}{day} =  \frac{2 + 1}{100} =  \frac{3}{100}  \\ days =  \frac{100}{3}   \: or \:  \: 33.3days \\
ANSWER IS 33.3 DAYS
PLESE MARK ME AS BRAINLIEST

05102005rajat78: Mark me as BRAINLIEST
Answered by RealSweetie
0

Then a do in 1day =1/50

then b do in 1 day=1/100

they together do In 1 day =1/50+1/100

=3/100

they together do the full work in 100/3 days