A can do a piece of work in 50 days and B can finish it in 40 days. they worked together for 10 days then A left the work. in how many days will B finish the remaining work?
Answers
Answered by
0
Step-by-step explanation:
Work done by A in 1 day = 1/50
Work done by B in 1 day = 1/40
Work done by A and B in 1 day = 1/50 + 1/40 = 9/200
Work done by A and B in 10 days = 10×(9/200) = 9/20
Work left = 1-9/20 = 11/20
A lefts here.
As Work done by B in 1 day = 1/40
No. of days B will take to complete the remaining work = 11/20 ÷ 1/40 = 11/20 × 40 = 22 days.