Math, asked by PrabhGhuman2, 7 months ago

A can do a piece of work in 6 days and B can do the same work in 8 days how long will they take to complete the work together​

Answers

Answered by merinmathew232
5

Answer:  3\frac{3}{7} Days

Step-by-step explanation:

A can do a piece of work in 6 days

1 day work of A = \frac{1}{6}

B can do the same work in 8 days

1 day work of B= \frac{1}{8}

1 day work of both A and B = \frac{1}{6} + \frac{1}{8}

                                           = \frac{4 + 3}{24}

                                           = \frac{7}{24}

∴A and B can complete the work in 24/7 days = 3\frac{3}{7} Days

Thank U : )

Mark As the BRAINLIEST if U find my answer Helpful.

Similar questions