A can do a piece of work in 6 days , B in 10 days and C in 15 days. they jointly work and earn Rs . 300. the sum of their wages for two days
Aishwarya98:
hope this helps you..
Answers
Answered by
1
By using LCM method,
LCM of 6,10,15 is 30
A- 6 days - 5 work per day
B-10 days - 3 work per day
C - 15 days - 2 work per day
They get Rs.300 for their completion of work in 3 days.
For 2 days, they will get Rs.200
Answered by
2
- Given A can do a piece of work in 6 days , B in 10 days and C in 15 days i.e., A=1/6,B=1/10,C=1/5
- Let x be no.of days taken to complete work by them i.e.,
- x[(1/6)+(1/10)+(1/15)]= 1
- From this we get x=3 days
- For 3 days they take 300.Hence for 2 days they will 200