Math, asked by nlpratik234, 1 year ago

A can do a piece of work in 6 days , B in 10 days and C in 15 days. they jointly work and earn Rs . 300. the sum of their wages for two days


Aishwarya98: hope this helps you..

Answers

Answered by Aishwarya98
1

By using LCM method,

LCM of 6,10,15 is 30

A- 6 days - 5 work per day

B-10 days - 3 work per day

C - 15 days - 2 work per day

They get Rs.300 for their completion of work in 3 days.

For 2 days, they will get Rs.200


Aishwarya98: mark me as brainliest..
Answered by anr4u97
2
  1. Given A can do a piece of work in 6 days , B in 10 days and C in 15 days i.e., A=1/6,B=1/10,C=1/5
  2. Let x be no.of days taken to complete work by them i.e.,
  3. x[(1/6)+(1/10)+(1/15)]= 1
  4. From this we get x=3 days
  5. For 3 days they take 300.Hence for 2 days they will 200