Math, asked by nisha2890, 10 months ago

A can do a piece of work in 60 days, which B can do in 40 days. Both started the work but A left 10 days before the completion of the work. The work was finished in how many days?​

Answers

Answered by BRAINLYARMY001
1

Answer:

hii

your answer is here !

Step-by-step explanation:

A left the job 10 days before the completion.

So, B worked alone for the last 10 days.

First,

we will calculate B’s 10 days work,

which he did alone.

In 10 days B will do 10 × 1/40 = 1/4th of the work.

Remaining work 1 - ¼ = ¾ (Which A and B have done together).

A and B can do 1/60 + 1/40 work in 1 day.

Their one-day’s work is 1/60 + 1/40 = (2 + 3)/120 = 5/120 = 1/24.

They can finish the work in 24 days.

They would have done three-fourth of the work in 24 × 3/4 = 18 days

.

⇒ Total days = 18 + 10 = 28.

follow \:  \:  \: me

Answered by Anonymous
0

A's 1 day work = 1/60

B's 1 day work = 1/40

Together they can finish in = 1/60 + 1/40 = 1/24

Therefore, together they take 24 days to complete the work.

Now, if A left 10 days before completion then,

Number of days A & B worked together = 24-10 = 14 days.

Percent completion of both A & B working together for 14 days is,

(1/24) × 14 × 100 = 58.33%

B's 1 day efficiency = 1/40 ×100 = 2.5%

& the left work is = 100 - 58.33 = 41.67%

Therefore, no. of days further B will take to complete the work is,

41.67/2.5 = 16.67 days

Therefore, the work finished at 14+16.67 = 30.67 days.

ItzDopeGirl

Similar questions