Math, asked by luck65, 1 year ago

A can do a piece of work in 60 days while B can do it in 75 days. They begin together but 20 days before the completion of the work, A leaves off. How many days B finishes the remaining work?​

Answers

Answered by BBB5035
1

in 65 days

hope this helps you...